Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-10-29 03-0E3604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 28% 03-NEV-80-R59.4/R59.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-07 BERKELEY ENGINEERING CO INC P O BOX 7069 BERKELEY CA 94707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 87,362.59 87,362.59 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 87,362.59 87,362.59 5. Mobilization 33,750.00 33,750.00 6. Total Work Completed 121,112.59 7. Deductions 8. a.Contract Retentions -8,736.26 -8,736.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 112,376.33 112,376.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,376.33