Dept. of Trans. PROGRESS Serial No. Contract No. 07-080-15-33 03-0E3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 22% 03-YOL-16-35.2/35.4 Federal Project: ACST-P016(31) PH-P016(31) Progress payment No. 02 Payment period ending: 03-20-07 MC GUIRE AND HESTER 9009 RAILROAD AVENUE OAKLAND CA 94603 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 149,209.70 138,414.70 2.a. Extra Work 2,609.17 2,609.17 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 151,818.87 141,023.87 5. Mobilization 6. Total Work Completed 151,818.87 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 146,818.87 136,023.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,023.87