Dept. of Trans. FINAL Serial No. Contract No. 08-177-10-59 03-0E4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-51-0.2/1.1 Federal Project: NONE Progress payment No. 07 Payment period ending: 11-14-06 MARTIN BROTHERS CONSTRUCTION 20 LIGHT SKY COURT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 700,122.15 0.00 2.a. Extra Work 64,410.37 0.00 b. Adjustment Comp. 35,845.11 0.00 3. Materials on Hand 4. Earned Subject to Retention 800,377.63 0.00 5. Mobilization 25,000.00 0.00 6. Total Work Completed 825,377.63 7. Deductions 0.00 18,000.00 8. a.Contract Retentions -29,209.64 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 29,209.64 0.00 9. Total pay to Contractor 825,377.63 18,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,000.00