Dept. of Trans. PROGRESS Serial No. Contract No. 09-054-13-10 03-0E5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 82% 03-PLA-80-1.5/2.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-20-09 PARKER LANDSCAPE DEVELOPMENT INC 6251 SKY CREEK DRIVE SUITE A SACRAMENTO CA 95828 Escrow No. 02406 Total Estimate This Estimate 1. Contract Itms Without Mobil. 235,786.37 42,396.92 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 235,786.37 42,396.92 5. Mobilization 6. Total Work Completed 235,786.37 7. Deductions -4,000.00 -4,000.00 8. a.Contract Retentions -11,789.32 -2,119.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 219,997.05 36,277.07 10. Reduction Amt to Escrow 11. Payment to Escrow 11,780.00 12. Net Pymt. this Estimate 36,277.07