Dept. of Trans. PROGRESS Serial No. Contract No. 09-079-11-47 03-0E5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 78% 03-PLA-80-1.5/2.3 Federal Project: NONE Progress payment No. 05 Payment period ending: 03-20-09 PARKER LANDSCAPE DEVELOPMENT INC 6251 SKY CREEK DRIVE SUITE A SACRAMENTO CA 95828 Escrow No. 02406 Total Estimate This Estimate 1. Contract Itms Without Mobil. 262,336.14 26,549.77 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 262,336.14 26,549.77 5. Mobilization 6. Total Work Completed 262,336.14 7. Deductions 0.00 4,000.00 8. a.Contract Retentions -13,116.81 -1,327.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 249,219.33 29,222.28 10. Reduction Amt to Escrow 11. Payment to Escrow 13,110.00 12. Net Pymt. this Estimate 29,222.28