Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-14-05 03-0E6804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 90% 03-YOL-5-0.4/5.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-20-06 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,951,191.50 1,020,898.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -488,262.00 4. Earned Subject to Retention 2,951,191.50 532,636.00 5. Mobilization 296,000.00 0.00 6. Total Work Completed 3,247,191.50 7. Deductions -620.00 0.00 8. a.Contract Retentions -147,559.58 -26,631.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,099,011.92 506,004.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 506,004.20