Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-242-10-48 03-0E7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-16-4.6/ .0 Federal Project: ACST-P016(29) PH-P016(29) STPL-6203(19) Progress payment No. 08 Payment period ending: 06-11-07 PRISM ENGINEERING 630 REED STREET SANTA CLARA CA 95050 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 874,406.50 0.00 2.a. Extra Work b. Adjustment Comp. -894.05 -894.05 3. Materials on Hand 4. Earned Subject to Retention 873,512.45 -894.05 5. Mobilization 6. Total Work Completed 873,512.45 7. Deductions -39,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 834,512.45 9,105.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,105.95