Dept. of Trans. PROGRESS Serial No. Contract No. 09-021-14-14 03-0E8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 55% 03-SAC-50-R5.3/15.7 Federal Project: ACST-P050(113) PE-P050(113) Progress payment No. 15 Payment period ending: 01-20-09 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY RD 4 FLR ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 267,855.32 1,706.75 2.a. Extra Work 15,638.82 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 283,494.14 1,706.75 5. Mobilization 35,747.82 0.00 6. Total Work Completed 319,241.96 7. Deductions -2,154.88 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 317,087.08 1,706.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,706.75