Dept. of Trans. FINAL Serial No. Contract No. 07-298-12-41 03-0E9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-160-19.7/20.9 Federal Project: NONE Progress payment No. 07 Payment period ending: 09-18-06 ASHRON CONSTRUCTION AND RESTORATION INC 713 N SHORELINE BLVD MOUNTAIN VIEW CA 94043 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 168,620.28 20,900.00 2.a. Extra Work 118,071.32 0.00 b. Adjustment Comp. -15,673.32 -19,530.00 3. Materials on Hand 4. Earned Subject to Retention 271,018.28 1,370.00 5. Mobilization 6. Total Work Completed 271,018.28 7. Deductions 8. a.Contract Retentions -3,778.33 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 3,778.33 0.00 9. Total pay to Contractor 271,018.28 1,370.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,370.00