Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-258-10-36 03-0F0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-20-R6.6/ .0 Federal Project: STP-P020(156) Progress payment No. 04 Payment period ending: 09-06-12 KNIFE RIVER COMPANY 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 912,724.70 10,687.55 2.a. Extra Work 49,283.95 49,283.95 b. Adjustment Comp. -2,180.53 -2,180.53 3. Materials on Hand 4. Earned Subject to Retention 959,828.12 57,790.97 5. Mobilization 6. Total Work Completed 959,828.12 7. Deductions -25,000.00 -25,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 934,828.12 32,790.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,790.97