Dept. of Trans. PROGRESS Serial No. Contract No. 12-262-13-51 03-0F0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 51% 03-PLA-267-0.4/1.2 Federal Project: ACST-P267(21) P Progress payment No. 03 Payment period ending: 09-17-12 WESTERN ENGINEERING CONTRACTORS, INC P O BOX 1387 LOOMIS, CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 576,003.52 369,052.52 2.a. Extra Work 32,342.86 32,342.86 b. Adjustment Comp. -6,550.67 -6,550.67 3. Materials on Hand 4. Earned Subject to Retention 601,795.71 394,844.71 5. Mobilization 6. Total Work Completed 601,795.71 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 601,795.71 394,844.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 394,844.71