Dept. of Trans. PROGRESS Serial No. Contract No. 12-053-13-14 03-0F1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 40% 03-SUT-99-27.0/ .0 Federal Project: CML6-2030(43) Progress payment No. 03 Payment period ending: 02-17-12 BIONDI PAVING INC 8150 37TH AVENUE SACRAMENTO CA 95824 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 480,653.05 118,607.55 2.a. Extra Work 4,790.52 4,790.52 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 485,443.57 123,398.07 5. Mobilization 6. Total Work Completed 485,443.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 485,443.57 123,398.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 123,398.07