Dept. of Trans. PROGRESS Serial No. Contract No. 12-143-08-14 03-0F1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 03-SUT-99-27.0/ .0 Federal Project: CML6-2030(43) Progress payment No. 06 Payment period ending: 05-17-12 BIONDI PAVING INC 8150 37TH AVENUE SACRAMENTO CA 95824 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 502,404.05 5,202.00 2.a. Extra Work 14,690.61 0.00 b. Adjustment Comp. 4,614.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 521,709.16 5,202.00 5. Mobilization 6. Total Work Completed 521,709.16 7. Deductions -8,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 513,709.16 5,202.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,202.00