Dept. of Trans. PROGRESS Serial No. Contract No. 14-265-08-12 03-0F2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 95% 03-SAC-50-1.6/ .0 Federal Project: BHNH-P050(132) Progress payment No. 09 Payment period ending: 09-18-14 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,066,614.23 263,397.50 2.a. Extra Work 316,324.26 1,236.97 b. Adjustment Comp. 6,778,651.40 32,749.64 3. Materials on Hand 4. Earned Subject to Retention 22,161,589.89 297,384.11 5. Mobilization 1,700,000.00 0.00 6. Total Work Completed 23,861,589.89 7. Deductions -44,100.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,817,489.89 297,384.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,384.11