Dept. of Trans. PROGRESS Serial No. Contract No. 21-084-13-39 03-0F2504 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 20% Location: Federal Project: 03-YOL-80-R11.1/11.7 ACIM-080-2(250) Progress payment No. 004 Payment period ending: 03-20-21 AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,300,816.00 1,298,583.42 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 408,917.00 -43,010.00 4. Earned Subject to Retention 2,709,733.00 1,255,573.42 5. Mobilization 937,500.00 312,500.00 6. Total Work Completed 3,238,316.00 7. Deductions -19,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,628,233.00 1,562,073.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,562,073.42