Dept. of Trans. PROGRESS Serial No. Contract No. 22-082-14-57 03-0F2504 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 94% Location: Federal Project: 03-YOL-80-R11.1/11.7 ACIM-080-2(250) Progress payment No. 018 Payment period ending: 03-20-22 AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,552,192.03 746,528.20 2. a. Extra Work 748,140.15 218,374.55 b. Adustment Comp. 116,326.52 0.00 3. Materials on Hand 29,997.60 -70,506.40 4. Earned Subject to Retention 16,446,656.30 894,396.35 5. Mobilization 1,250,000.00 0.00 6. Total Work Completed 17,666,658.70 7. Deductions -23,300.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,673,356.30 894,396.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 894,396.35