Dept. of Trans. PROGRESS Serial No. Contract No. 21-231-13-42 03-0F2804 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 26% Location: Federal Project: 03-SAC-99-7.1/9.4 NHS Progress payment No. 007 Payment period ending: 08-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,864,941.82 2,422,630.84 2. a. Extra Work 30,198.02 15,206.76 b. Adustment Comp. 3. Materials on Hand 104,522.00 -11,862.16 4. Earned Subject to Retention 19,999,661.84 2,425,975.44 5. Mobilization 4,451,081.84 0.00 6. Total Work Completed 24,346,221.68 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,447,743.68 2,422,975.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,422,975.44