Dept. of Trans. PROGRESS Serial No. Contract No. 22-054-11-16 03-0F2804 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 48% Location: Federal Project: 03-SAC-99-7.1/9.4 NHS Progress payment No. 013 Payment period ending: 02-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,386,342.06 1,044,342.18 2. a. Extra Work 268,651.56 11,577.23 b. Adustment Comp. 204,556.40 0.00 3. Materials on Hand 224,513.25 -25,751.75 4. Earned Subject to Retention 31,084,063.27 1,030,167.66 5. Mobilization 4,685,349.30 0.00 6. Total Work Completed 35,544,899.32 7. Deductions -12,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 35,757,412.57 1,050,167.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,050,167.66