Dept. of Trans. PROGRESS Serial No. Contract No. 20-237-14-00 03-0F2844 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 39% Location: Federal Project: 03-SAC-99-7.1/9.4 NONE Progress payment No. 003 Payment period ending: 08-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,642,177.98 3,695,869.24 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 217,355.00 -64,343.00 4. Earned Subject to Retention 6,859,532.98 3,631,526.24 5. Mobilization 1,299,336.44 0.00 6. Total Work Completed 7,941,514.42 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,158,869.42 3,631,526.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,631,526.24