Dept. of Trans. PROGRESS Serial No. Contract No. 20-269-09-52 03-0F2844 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 61% Location: Federal Project: 03-SAC-99-7.1/9.4 NONE Progress payment No. 004 Payment period ending: 09-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,183,948.07 1,541,770.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 123,275.00 -94,080.00 4. Earned Subject to Retention 8,307,223.07 1,447,690.10 5. Mobilization 1,367,722.57 68,386.13 6. Total Work Completed 9,551,670.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,674,945.64 1,516,076.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,516,076.23