Dept. of Trans. PROGRESS Serial No. Contract No. 20-296-09-41 03-0F2844 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 76% Location: Federal Project: 03-SAC-99-7.1/9.4 NONE Progress payment No. 005 Payment period ending: 10-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,258,994.64 1,075,046.56 2. a. Extra Work 23,853.89 23,853.89 b. Adustment Comp. 3. Materials on Hand 43,514.00 -79,761.00 4. Earned Subject to Retention 9,326,362.53 1,019,139.45 5. Mobilization 1,367,722.57 0.00 6. Total Work Completed 10,650,571.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,694,085.10 1,019,139.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,019,139.45