Dept. of Trans. PROGRESS Serial No. Contract No. 21-145-15-07 03-0F2844 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 98% Location: Federal Project: 03-SAC-99-7.1/9.4 NONE Progress payment No. 012 Payment period ending: 05-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,381,998.68 452,389.50 2. a. Extra Work 644,432.67 111,900.84 b. Adustment Comp. 3. Materials on Hand 0.00 -41,430.00 4. Earned Subject to Retention 15,026,431.35 522,860.34 5. Mobilization 1,367,722.57 0.00 6. Total Work Completed 16,394,153.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,394,153.92 522,860.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 522,860.34