Dept. of Trans. PROGRESS Serial No. Contract No. 21-235-11-18 03-0F2844 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 98% Location: Federal Project: 03-SAC-99-7.1/9.4 NONE Progress payment No. 015 Payment period ending: 08-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,842,336.62 24,877.13 2. a. Extra Work 697,342.84 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 15,539,679.46 24,877.13 5. Mobilization 1,367,722.57 0.00 6. Total Work Completed 16,907,402.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,907,402.03 24,877.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,877.13