Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-275-16-08 03-0F2854 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SAC-99-7.1/9.4 NONE Progress payment No. 005 Payment period ending: 06-18-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,736,758.27 0.00 2. a. Extra Work 250,560.93 63,899.12 b. Adustment Comp. -106,570.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,880,748.62 63,899.12 5. Mobilization 917,537.08 0.00 6. Total Work Completed 8,798,285.70 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,778,285.70 63,899.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,899.12