Dept. of Trans. PROGRESS Serial No. Contract No. 20-296-10-26 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 17% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 004 Payment period ending: 10-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,080,918.12 7,240,769.73 2. a. Extra Work 53,993.90 39,349.38 b. Adustment Comp. 3. Materials on Hand 74,420.00 -3,595,045.00 4. Earned Subject to Retention 21,209,332.02 3,685,074.11 5. Mobilization 5,841,695.45 0.00 6. Total Work Completed 26,976,607.47 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,051,027.47 3,685,074.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,685,074.11