Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-09-16 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 22% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 005 Payment period ending: 11-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,674,133.33 1,593,215.20 2. a. Extra Work 2,430,812.60 2,376,818.70 b. Adustment Comp. 3. Materials on Hand 45,365.00 -29,055.00 4. Earned Subject to Retention 25,150,310.93 3,940,978.90 5. Mobilization 5,841,695.45 0.00 6. Total Work Completed 30,946,641.38 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,992,006.38 3,940,978.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,940,978.90