Dept. of Trans. PROGRESS Serial No. Contract No. 20-356-12-31 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 26% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 007 Payment period ending: 12-20-20 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,907,410.16 2,233,276.82 2. a. Extra Work 2,430,812.60 0.00 b. Adustment Comp. 3. Materials on Hand 33,883.00 -83,544.00 4. Earned Subject to Retention 27,372,105.76 2,149,732.82 5. Mobilization 5,841,695.45 0.00 6. Total Work Completed 33,179,918.21 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,208,801.21 2,144,732.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,144,732.82