Dept. of Trans. PROGRESS Serial No. Contract No. 21-172-08-25 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 50% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 013 Payment period ending: 06-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,223,973.95 956,006.51 2. a. Extra Work 3,043,667.41 18,279.85 b. Adustment Comp. 3. Materials on Hand 2,650,090.00 -920,730.00 4. Earned Subject to Retention 39,917,731.36 53,556.36 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 43,416,794.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,066,884.46 53,556.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,556.36