Dept. of Trans. PROGRESS Serial No. Contract No. 21-203-11-18 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 56% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 014 Payment period ending: 07-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,032,682.73 4,808,708.80 2. a. Extra Work 3,067,207.76 23,540.35 b. Adustment Comp. 3. Materials on Hand 2,581,946.50 -68,143.50 4. Earned Subject to Retention 44,681,836.99 4,764,105.65 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 48,249,043.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 50,830,990.09 4,764,105.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,764,105.65