Dept. of Trans. PROGRESS Serial No. Contract No. 21-266-09-58 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 66% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 016 Payment period ending: 09-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,469,906.75 1,176,969.12 2. a. Extra Work 3,123,172.55 55,964.79 b. Adustment Comp. 3. Materials on Hand 2,581,946.00 -0.50 4. Earned Subject to Retention 50,175,025.30 1,232,933.41 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 53,742,232.40 7. Deductions -8,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 56,316,178.40 1,239,933.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,239,933.41