Dept. of Trans. PROGRESS Serial No. Contract No. 21-300-12-14 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 70% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 017 Payment period ending: 10-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,571,660.61 4,101,753.86 2. a. Extra Work 3,163,804.05 40,631.50 b. Adustment Comp. 3. Materials on Hand 0.00 -2,581,946.00 4. Earned Subject to Retention 51,735,464.66 1,560,439.36 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 57,884,617.76 7. Deductions -8,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 57,876,617.76 1,560,439.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,560,439.36