Dept. of Trans. PROGRESS Serial No. Contract No. 21-326-09-38 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 73% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 018 Payment period ending: 11-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,211,543.63 639,883.01 2. a. Extra Work 3,163,804.05 0.00 b. Adustment Comp. -3,748.01 -3,748.01 3. Materials on Hand 4. Earned Subject to Retention 52,371,599.67 636,135.00 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 58,520,752.77 7. Deductions -13,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,507,752.77 631,135.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 631,135.00