Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-14-10 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 94% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 023 Payment period ending: 04-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,584,231.11 635,226.04 2. a. Extra Work 3,170,483.09 6,679.04 b. Adustment Comp. -43,367.29 0.00 3. Materials on Hand 4. Earned Subject to Retention 58,711,346.91 641,905.08 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 64,860,500.01 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 64,855,500.01 636,905.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 636,905.08