Dept. of Trans. PROGRESS Serial No. Contract No. 22-237-11-21 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 027 Payment period ending: 08-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,285,310.77 273,142.37 2. a. Extra Work 3,181,940.11 0.00 b. Adustment Comp. -43,367.29 0.00 3. Materials on Hand 4. Earned Subject to Retention 59,423,883.59 273,142.37 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 65,573,036.69 7. Deductions -9,000.00 6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 65,564,036.69 279,142.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 279,142.37