Dept. of Trans. FINAL Serial No. Contract No. 23-362-07-56 03-0F2864 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SAC-99-7.1/9.4 ACNH-P099(663) Progress payment No. 031 Payment period ending: 08-17-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,347,194.03 0.00 2. a. Extra Work 3,496,320.01 0.00 b. Adustment Comp. -283,053.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 59,560,460.06 0.00 5. Mobilization 6,149,153.10 0.00 6. Total Work Completed 65,709,613.16 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 65,704,613.16 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00