Dept. of Trans. PROGRESS Serial No. Contract No. 18-054-14-24 03-0F3104 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 67% Location: Federal Project: 03-ED-49-24.0 ACST-P049-1(69) Progress payment No. 012 Payment period ending: 02-20-18 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,157,330.50 432,639.00 2. a. Extra Work 198,881.36 60,268.41 b. Adustment Comp. 30,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,386,211.86 492,907.41 5. Mobilization 1,642,646.00 0.00 6. Total Work Completed 12,028,857.86 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,023,857.86 492,907.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 492,907.41