Dept. of Trans. FINAL Serial No. Contract No. 11-025-14-42 03-0F5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-99-3.7/ .0 Federal Project: HSNH-X067(70) Progress payment No. 04 Payment period ending: 09-23-10 MARTIN GENERAL ENGINEERING INC 12485 QUICKSILVER DRIVE RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 332,800.95 0.00 2.a. Extra Work 14,000.00 0.00 b. Adjustment Comp. -4,370.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 342,430.95 0.00 5. Mobilization 6. Total Work Completed 342,430.95 7. Deductions 0.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 342,430.95 5,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,000.00