Dept. of Trans. PROGRESS Serial No. Contract No. 16-112-11-34 03-0F6904 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 8% Location: Federal Project: 03-BUT-70-24.3 BRST-P070(100) Progress payment No. 005 Payment period ending: 04-20-16 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 479,563.90 439,577.50 2. a. Extra Work b. Adustment Comp. 137,260.00 114,973.00 3. Materials on Hand 90,150.00 0.00 4. Earned Subject to Retention 706,973.90 554,550.50 5. Mobilization 248,900.00 117,900.00 6. Total Work Completed 865,723.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 955,873.90 672,450.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 672,450.50