Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-13-39 03-0F7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 7% 03-YOL-80-0.2/5.7 Federal Project: ACHS-802(358) IM-802(358) Progress payment No. 03 Payment period ending: 06-16-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,110.00 18,360.00 2.a. Extra Work 21,328.47 10,350.65 b. Adjustment Comp. 104,911.95 104,911.95 3. Materials on Hand 4. Earned Subject to Retention 148,350.42 133,622.60 5. Mobilization 6. Total Work Completed 148,350.42 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 148,350.42 133,622.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,622.60