Dept. of Trans. PROGRESS Serial No. Contract No. 16-362-09-43 03-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 88% Location: Federal Project: 03-VAR STP-000C-0(404) Progress payment No. 010 Payment period ending: 12-20-16 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 957411508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,161,141.83 141,580.28 2. a. Extra Work 40,012.64 1,944.81 b. Adustment Comp. 2,970.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,204,124.47 143,525.09 5. Mobilization 250,000.00 0.00 6. Total Work Completed 2,454,124.47 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,454,124.47 143,525.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,525.09