Dept. of Trans. PROGRESS Serial No. Contract No. 15-233-09-35 03-0G0904 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 8% Location: Federal Project: 03-YUB-49-0.0/6.4 NONE Progress payment No. 001 Payment period ending: 08-20-15 BALDWIN CONTRACTING CO., INC. DBA KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 81,142.50 81,142.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 81,142.50 81,142.50 5. Mobilization 6. Total Work Completed 81,142.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 81,142.50 81,142.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,142.50