Dept. of Trans. FINAL Serial No. Contract No. 16-139-14-13 03-0G1504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-NEV-49-0.0/14.4 NH-P049(160) Progress payment No. 008 Payment period ending: 12-09-15 TEICHERT CONSTRUCTION PO BOX 1118 STOCKTON CA 952011118 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,186,119.00 0.00 2. a. Extra Work 696,875.49 64,685.74 b. Adustment Comp. -2,596.10 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,880,398.39 64,685.74 5. Mobilization 472,500.00 0.00 6. Total Work Completed 4,352,898.39 7. Deductions 0.00 21,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,352,898.39 85,685.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,685.74