Dept. of Trans. FINAL Serial No. Contract No. 18-002-11-23 03-0G3204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-NEV-20-0.9/0.9 NONE Progress payment No. 006 Payment period ending: 10-30-17 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC. 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 605,129.92 0.00 2. a. Extra Work 26,886.24 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 632,016.16 0.00 5. Mobilization 71,000.00 0.00 6. Total Work Completed 703,016.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 703,016.16 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00