Dept. of Trans. FINAL Serial No. Contract No. 16-250-15-23 03-0G3504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-80-69.3/69.8 NONE Progress payment No. 004 Payment period ending: 06-24-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 482,642.00 0.00 2. a. Extra Work 2,306.51 2,306.51 b. Adustment Comp. 18,019.79 -23,521.42 3. Materials on Hand 4. Earned Subject to Retention 502,968.30 -21,214.91 5. Mobilization 6. Total Work Completed 502,968.30 7. Deductions 0.00 48,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 502,968.30 26,785.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,785.09