Dept. of Trans. PROGRESS Serial No. Contract No. 18-052-15-04 03-0G7104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 67% Location: Federal Project: 03-YOL-999 ACNH-X113(34) Progress payment No. 006 Payment period ending: 02-20-18 FBD VANGUARD CONSTRUCTION INC 651 ENTERPRISE CT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,591,252.31 138,688.50 2. a. Extra Work 1,987.69 1,987.69 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,593,240.00 140,676.19 5. Mobilization 250,000.00 0.00 6. Total Work Completed 1,843,240.00 7. Deductions -29,156.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,814,084.00 140,676.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,676.19