Dept. of Trans. PROGRESS Serial No. Contract No. 18-332-10-16 03-0G8604 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 83% Location: Federal Project: 03-GLE-162-45.1/45.1 NONE 03-BUT-70 Progress payment No. 003 Payment period ending: 11-20-18 TPA CONSTRUCTION INC 2406 CLUBHOUSE DRIVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 229,072.00 42,850.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 229,072.00 42,850.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 259,072.00 7. Deductions -3,067.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 256,005.00 44,850.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,850.00