Dept. of Trans. PROGRESS Serial No. Contract No. 18-325-15-14 03-0G8704 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 41% Location: Federal Project: 03-ED-50-18.5 NONE Progress payment No. 006 Payment period ending: 11-20-18 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,657,199.45 203,480.00 2. a. Extra Work 54,681.38 54,681.38 b. Adustment Comp. 3. Materials on Hand 14,480.00 0.00 4. Earned Subject to Retention 2,726,360.83 258,161.38 5. Mobilization 275,000.00 0.00 6. Total Work Completed 2,986,880.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,001,360.83 258,161.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 258,161.38