Dept. of Trans. PROGRESS Serial No. Contract No. 23-144-17-33 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 64% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 038 Payment period ending: 05-20-23 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 266,651,532.50 5,281,132.50 2. a. Extra Work 1,513,352.32 8,978.85 b. Adustment Comp. -2,151,518.17 3,250,000.00 3. Materials on Hand 2,089,207.12 134,800.00 4. Earned Subject to Retention 268,102,573.77 8,674,911.35 5. Mobilization 6. Total Work Completed 266,013,366.65 7. Deductions -622,570.80 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 267,480,002.97 8,674,911.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,674,911.35