Dept. of Trans. PROGRESS Serial No. Contract No. 23-171-09-02 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 66% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 039 Payment period ending: 06-20-23 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 273,291,707.50 6,640,175.00 2. a. Extra Work 1,513,352.32 0.00 b. Adustment Comp. -2,181,838.17 -30,320.00 3. Materials on Hand 2,089,207.12 0.00 4. Earned Subject to Retention 274,712,428.77 6,609,855.00 5. Mobilization 6. Total Work Completed 272,623,221.65 7. Deductions -608,513.28 14,057.52 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 274,103,915.49 6,623,912.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,623,912.52