Dept. of Trans. PROGRESS Serial No. Contract No. 23-233-10-18 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 70% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 042 Payment period ending: 08-20-23 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 284,197,152.50 3,546,050.00 2. a. Extra Work 2,263,065.21 80,806.61 b. Adustment Comp. -540,156.08 -200.00 3. Materials on Hand 3,518,533.93 -186,436.38 4. Earned Subject to Retention 289,438,595.56 3,440,220.23 5. Mobilization 6. Total Work Completed 285,920,061.63 7. Deductions -608,513.28 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 288,830,082.28 3,440,220.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,440,220.23